Project Overview:The total height of the project is 206 meters (excluding underground engineering), and each floor of the building has an angle change, with a beautiful and complex appearance.. Construction elevator configuration requirements for the main building: frequency conversion speed control elevator, lifting speed 0-56m/min, rated load capacity not less than 2T, cage size not less than 3.8 * 1.5 * 2.5, maximum lifting height not less than 206m
Number of elevators used:4 units, specification: SC200/200
Main engineering challenges solved:
1. The surface of the building presents irregular changes, with beautiful shapes and complex structures;
2. The project has a high height and requires high operating speed;
3. The foundations of the two construction elevators need to be arranged on the bottom foundation of the podium building, without affecting the engineering foundation, and the positioning should be accurate;
4. Multiple sizes and structures of attachment devices are combined.