Case:
1. Project Name: Inner Mongolia Xilinhot Jinshan Power Plant Cooling Tower Project
Project Overview: The total height of the project is 189m (above ground level), with a cooling tower bottom diameter of 20.5m and an upper diameter of less than 9.0m. Construction is carried out inside the tower.
Number of elevators used: 2, specification: SC200/200 smoke tower multifunctional construction elevator
The main engineering challenges to be solved are:
1. One machine with multiple uses, equipped with steel bar transport device and concrete transport device on the basis of traditional construction elevators, can transport steel bars, concrete and construction personnel, greatly improving construction efficiency;
2. It is required to configure a professional unloading platform, where various materials and construction personnel can smoothly transition to the construction position through the platform after arriving at the construction layer; The platform can be raised on its own according to the progress of the project, and the amplitude can gradually decrease to meet the construction requirements;
3. To meet the construction requirements of smoke towers or similar buildings, steel bars can be lifted by their own lifting equipment on the ground and fixed in the steel cage; Once the construction site is reached, the steel bars can be lifted onto the construction platform;
4. The bottom of the cage can hang a concrete hopper, which can smoothly pour concrete into the ground. After the cage reaches the construction layer, it can smoothly receive its concrete on the construction platform.
5. The attachment distance is constantly changing and the distance is too long.
D-7 image
2. Project Name: Henan Shangqiu Minsheng Thermal Power Engineering Project
Project Overview: The total height of the project is 191m (above ground level), with a cooling tower bottom diameter of 22.0m and an upper diameter of less than 8.0m. Construction is carried out inside the tower.
Number of elevators used: 1 unit, specification: SC200/200 smoke tower multifunctional construction elevator
The main engineering challenges to be solved are:
1. One machine with multiple uses, equipped with steel bar transport device and concrete transport device on the basis of traditional construction elevators, can transport steel bars, concrete and construction personnel, greatly improving construction efficiency;
2. It is required to configure a professional unloading platform, where various materials and construction personnel can smoothly transition to the construction position through the platform after arriving at the construction layer; The platform can be raised on its own according to the progress of the project, and the amplitude can gradually decrease to meet the construction requirements;
3. To meet the construction requirements of smoke towers or similar buildings, steel bars can be lifted by their own lifting equipment on the ground and fixed in the steel cage; Once the construction site is reached, the steel bars can be lifted onto the construction platform;
4. The bottom of the cage can hang a concrete hopper, which can smoothly pour concrete into the ground. After the cage reaches the construction layer, it can smoothly receive its concrete on the construction platform.
5. The attachment distance is constantly changing and the distance is too long.
D-8 image